Water Treatment Plant Project - Update Page

May 19, 2023 - May has been a very productive month.  Penn-co Construction completed the base slab reinforcing steel and four (4) concrete placements to complete the base slab concrete.  Next, the Contractor will begin form work for the concrete walls of the foundation which will become the water reservoir used to store drinking water.



April 26, 2023 - The Water Treatment Plant excavation has been completed and the concrete mud slab has been placed. Workers are placing reinforcing steel for the base slab, which is expected to be completed by mid-May.  Following the base slab concrete placement, installation of the formwork will begin for the concrete walls of the water reservoir chambers.

 


March 30, 2023 – Penn-co Construction began excavating the foundation of the new Water Treatment Plant at 1000 Park Avenue. The foundation is approximately 3m (10’) deep and will house the new concrete Water Reservoir Chambers, which store drinking water after treatment. The Reservoir will store approximately 1400 m3 (1,400,000L) of water, which is enough to supply the Town for approximately 24 hours at peak season, but also provides the Fire Department with a large supply of water in the event of a fire without any service interruption to the Town.

Once constructed, the Reservoir will be approximately 1m above the road and will be finished with a grass covered roof (Green Roof). Construction of the Reservoir is expected to be ongoing until August 2023 at which point the above-grade steel structure construction will begin.